Activity ID Budgeted Hours Actual Hours Expended % Budgeted Labor $ Physical % Complete Active
010-010-010 : Site Mobilization 120.000

2.414

2.01

0.000 0.00 1
010-090-010 : Site Demobilization 150.000

33.984

22.65

0.000 0.00 1
200-100-010 : Soil Remediation of Site 200 0.000

10.582

INF

0.000 0.00 1
200-100-020 : Installation of MicroPiles for Site 200 0.000

5.17

INF

0.000 0.00 1
200-200-010 : Installation of Underground Piping for Site 200 320.000

0.836

0.26

0.000 0.00 1